Long Thanh Airport opens 24 December: air cargo timeline

Long Thanh Airport opens 24 December: air cargo timeline

In about a month, Long Thanh International Airport (Dong Nai) will receive its first commercial flight. Over the weekend (22 November) Vietnamese media again ran photos from inside the passenger terminal ahead of opening. For shippers, the key point is that the opening date is now 00:00 on 24 December 2026 (in July, Airports Corporation of Vietnam – ACV – had targeted 1 December) and the cargo terminal will open step by step.

Long Thanh opening in three phases

  1. Phase 1 – 24 December 2026 to end of March 2027 (winter schedule): the west wing and centre of passenger terminal T1 open, with about 20–30 flights a day, or 6–10% of design capacity. Based on slot registrations ACV published on 19 November, this phase has up to 226 flights a week: about 182 domestic flights by Vietnam Airlines and Vietjet plus 44 international flights by Vietnam Airlines.
  2. Phase 2 – April to October 2027 (summer 2027 schedule): all long-haul international flights, including cargo, move to Long Thanh.
  3. Phase 3 – from October 2027 (winter 2027–2028 schedule): operations continue to scale up.

When does the Long Thanh cargo terminal open?

  • Domestic cargo: part of cargo terminal 1 (CTB1) opens on 24 December 2026.
  • International cargo: from January 2027, except shipments to Europe and the US.
  • EU and US cargo: waits for RA3 (EU) and TSA (US) air cargo security approvals, expected around July 2027.
  • The remaining cargo terminal works continue and are signed off during 2027.

Road access to the airport

The Bien Hoa – Vung Tau expressway (component 1) and HCMC Ring Road 3 (component 3) are targeted for completion in December 2026; Dong Nai’s roads 25B and 25C are being accelerated to open together with the airport.

Sea Star’s view: what air shippers should do

  • Cargo to Europe and the US: keeps moving through Tan Son Nhat until at least mid-2027 – no change needed yet.
  • Domestic and Asian cargo: from 24 December (domestic) and January 2027 (international), the same route may fly from either airport depending on the airline. Always check the airport on the booking and air waybill (AWB).
  • Re-plan trucking time: Long Thanh is further from central HCMC than Tan Son Nhat; allow extra time to reach the cargo terminal before the airline’s cut-off.

Sea Star handles international air freight end to end, including booking, customs clearance and trucking to the right terminal. Related: the roadmap for moving international flights from Tan Son Nhat to Long Thanh.

Frequently asked questions

When does Long Thanh Airport officially open?

According to ACV, commercial operation is planned from 00:00 on 24 December 2026.

Can I ship to the US via Long Thanh from January 2027?

Not yet. Cargo to the US and Europe can only go through Long Thanh after TSA and RA3 approval, expected around July 2027.

Will Tan Son Nhat stop handling international cargo?

No. Tan Son Nhat keeps its existing routes during the transition; long-haul international flights are expected to move to Long Thanh from the summer 2027 schedule.

Need an air freight quote for December? Send Sea Star a request – we will help you choose the right airport and flight.

Sources: CafeF – Long Thành khai thác thương mại ngày 24/12 · CafeF – Hơn 220 chuyến/tuần 3 tháng đầu · VnExpress · Vietnam+

Related articles

Lach Huyen to add 6 container berths worth USD 1.5 billion News Lach Huyen to add 6 container berths worth USD 1.5 billion Year-end peak season 2026: 6 things importers and exporters should do now News Year-end peak season 2026: 6 things importers and exporters should do now Moving international flights from Tan Son Nhat to Long Thanh: what cargo shippers should know News Moving international flights from Tan Son Nhat to Long Thanh: what cargo shippers should know

Most read

  1. Lach Huyen to add 6 container berths worth USD 1.5 billion
  2. Year-end peak season 2026: 6 things importers and exporters should do now
  3. Container rates, 12 November: WCI down 2% to USD 4,305/FEU as Shanghai waiting times rise

💬 Thảo luận & Hỏi đáp chuyên gia (0)

Gửi câu hỏi hoặc bình luận